Capacity configuration
Jam and marmalade production line rated 7 tph
mid-capacity configuration for fresh fruit, semi-finished pulp and sugar: jams, compotes, jarred toppings. Figures below come from the same engine behind MCF Project Studio™, based on 2,200 production hours per year and a turnkey scope (process, sterilisation, packaging, palletising, utilities).
Reference figures
- Indicative CAPEX
- €3.20M – €4.30M
- Annual output
- 11,127 t/year of finished product
- EBITDA at full ramp-up
- €3.18M (13%)
- Estimated payback
- 1.1 years
- Contract to commissioning
- 12 months
Indicative values computed with the MCF Project Studio™ engine: they are not a contractual offer. The final budget comes from the feasibility study with mass balance and site layout.
Turnkey scope
- Mass balance, layout and machine specifications
- Manufacturing in Italy with in-house FAT before shipment
- Shipment, mechanical and electrical erection by MCF technicians
- Full-load commissioning (SAT), operator and maintenance training
- Recommended spares, remote support and on-site service worldwide
Contract to commissioning — 12 months
Phase 1 · 1 months
Studio di fattibilità e layout
Bilancio di materia, layout preliminare, budget di CAPEX.
Phase 2 · 1.5 months
Progettazione esecutiva
P&I, quadri elettrici, specifiche macchine e fornitori.
Phase 3 · 6 months
Costruzione e assemblaggio
Produzione in officina, pre-assemblaggio e FAT prima della spedizione.
Phase 4 · 2 months
Spedizione e installazione
Marcatura CE inclusa, trasporto su gomma.
Phase 5 · 1.5 months
Avviamento, SAT e formazione
Collaudo a pieno carico, formazione operatori e manutentori, consegna documentazione.
Frequently asked questions
How much does a jam and marmalade production line rated 7 tph cost?
Indicative CAPEX for a turnkey 7 tph line ranges from €3.20M to €4.30M, including process, sterilisation, packaging, palletising and utilities. The exact figure depends on formats, contact materials and automation level, defined during the feasibility study.
What is the annual output of a 7 tph line?
With 2,200 production hours per year and 85% line efficiency, estimated output is 11,127 t/year of finished product. The figure already accounts for the process yield declared for fresh fruit, semi-finished pulp and sugar.
How long before the line is running?
From contract signature to full-load start-up it takes about 12 months: feasibility study and layout, detailed engineering, manufacturing with in-house FAT, shipment and erection, then SAT and operator training on site.
Is a 1.1 years payback realistic?
It is the ratio between mid CAPEX and EBITDA at full ramp-up, computed with a 13% sector margin. In Project Studio you can change selling price, annual hours and financing structure and immediately see how the return moves.
Related configurations
Go deeper: technical hubs and references
Paths matching this line: technical page, case studies from the same industry and reference hubs.
- Food processing plants by capacity and by countryEvery configuration with hourly capacity, indicative CAPEX and commissioning time.
- Food & beverage process technologies: complete guideHow a line is engineered: mass balance, thermal treatment, filling and end of line.
- Industrial case studies of turnkey food plantsDocumented references with real capacity, line layout and contract-to-SAT timeline.
Need the exact figure for your site?
Open this configuration in Project Studio: change capacity, annual hours, country and financing structure and get the dossier with CAPEX, P&L and the 6-year plan.