Country project
Water bottling line in Nigeria
Domestic market of over 200 million consumers and a strong push for local processing. MCF Technology and SGE engineer, build in Italy and install in Nigeria complete lines for treated spring or well water, producing PET bottles from 0.25 to 2 litres.
Reference figures
- Reference capacity
- 20,000 bph
- Indicative CAPEX on site
- €3.75M – €5.05M
- Delivery and start-up
- 15 months
- Local requirements
- Unstable grid: generator set and stabilisation included, NAFDAC product registration.
- Logistics
- Discharge at Lagos (Apapa/Lekki), extended 24-month spare-parts package.
Indicative values computed with the MCF Project Studio™ engine: they are not a contractual offer. The final budget comes from the feasibility study with mass balance and site layout.
Turnkey scope
- Mass balance, layout and machine specifications
- Manufacturing in Italy with in-house FAT before shipment
- Shipment, mechanical and electrical erection by MCF technicians
- Full-load commissioning (SAT), operator and maintenance training
- Recommended spares, remote support and on-site service worldwide
Contract to commissioning — 15 months
Phase 1 · 1 months
Studio di fattibilità e layout
Bilancio di materia, layout preliminare, budget di CAPEX.
Phase 2 · 1.5 months
Progettazione esecutiva
P&I, quadri elettrici, specifiche macchine e fornitori.
Phase 3 · 7 months
Costruzione e assemblaggio
Produzione in officina, pre-assemblaggio e FAT prima della spedizione.
Phase 4 · 4 months
Spedizione e installazione
Pacchetto ricambi esteso e formazione operatori estesa.
Phase 5 · 1.5 months
Avviamento, SAT e formazione
Collaudo a pieno carico, formazione operatori e manutentori, consegna documentazione.
Frequently asked questions
How much does a water bottling line cost in Nigeria?
For a reference capacity of 20,000 bph, indicative CAPEX delivered in Nigeria ranges from €3.75M to €5.05M. The estimate includes the country factor for logistics, certification and erection supervision.
Who handles shipping, customs and erection in Nigeria?
Discharge at Lagos (Apapa/Lekki), extended 24-month spare-parts package. MCF Technology manages shipment, customs paperwork and erection with its own mechanical and electronic technicians, through to full-load commissioning and training of local operators.
Which certifications and electrical requirements apply in Nigeria?
Unstable grid: generator set and stabilisation included, NAFDAC product registration. Technical documentation, wiring diagrams and manuals are issued in the language required by the local authority, and machines are prepared for the grid available on site.
How long until the line is producing in Nigeria?
About 15 months from signature, including 2.5 extra months compared with an installation in Italy for shipping, customs and site supervision by our commissioning team.
Related configurations
Go deeper: technical hubs and references
Paths matching this line: technical page, case studies from the same industry and reference hubs.
- Food processing plants by capacity and by countryEvery configuration with hourly capacity, indicative CAPEX and commissioning time.
- Food & beverage process technologies: complete guideHow a line is engineered: mass balance, thermal treatment, filling and end of line.
- Industrial case studies of turnkey food plantsDocumented references with real capacity, line layout and contract-to-SAT timeline.
Need the exact figure for your site?
Open this configuration in Project Studio: change capacity, annual hours, country and financing structure and get the dossier with CAPEX, P&L and the 6-year plan.