Country project

Water bottling line in Kazakhstan

Abundant raw material and access to the whole Eurasian Economic Union. MCF Technology and SGE engineer, build in Italy and install in Kazakhstan complete lines for treated spring or well water, producing PET bottles from 0.25 to 2 litres.

Reference figures

Reference capacity
20,000 bph
Indicative CAPEX on site
€3.65M – €4.85M
Delivery and start-up
15 months
Local requirements
Mandatory EAC/TR CU certification, technical documentation in Russian, continental-climate design.
Logistics
Intermodal transport via Poti or the trans-Caspian railway.

Indicative values computed with the MCF Project Studio™ engine: they are not a contractual offer. The final budget comes from the feasibility study with mass balance and site layout.

Turnkey scope

  • Mass balance, layout and machine specifications
  • Manufacturing in Italy with in-house FAT before shipment
  • Shipment, mechanical and electrical erection by MCF technicians
  • Full-load commissioning (SAT), operator and maintenance training
  • Recommended spares, remote support and on-site service worldwide

Contract to commissioning15 months

  1. Phase 1 · 1 months

    Studio di fattibilità e layout

    Bilancio di materia, layout preliminare, budget di CAPEX.

  2. Phase 2 · 1.5 months

    Progettazione esecutiva

    P&I, quadri elettrici, specifiche macchine e fornitori.

  3. Phase 3 · 7 months

    Costruzione e assemblaggio

    Produzione in officina, pre-assemblaggio e FAT prima della spedizione.

  4. Phase 4 · 3.5 months

    Spedizione e installazione

    Documentazione EAC/GOST e certificazione locale.

  5. Phase 5 · 1.5 months

    Avviamento, SAT e formazione

    Collaudo a pieno carico, formazione operatori e manutentori, consegna documentazione.

Frequently asked questions

How much does a water bottling line cost in Kazakhstan?

For a reference capacity of 20,000 bph, indicative CAPEX delivered in Kazakhstan ranges from €3.65M to €4.85M. The estimate includes the country factor for logistics, certification and erection supervision.

Who handles shipping, customs and erection in Kazakhstan?

Intermodal transport via Poti or the trans-Caspian railway. MCF Technology manages shipment, customs paperwork and erection with its own mechanical and electronic technicians, through to full-load commissioning and training of local operators.

Which certifications and electrical requirements apply in Kazakhstan?

Mandatory EAC/TR CU certification, technical documentation in Russian, continental-climate design. Technical documentation, wiring diagrams and manuals are issued in the language required by the local authority, and machines are prepared for the grid available on site.

How long until the line is producing in Kazakhstan?

About 15 months from signature, including 2 extra months compared with an installation in Italy for shipping, customs and site supervision by our commissioning team.

Go deeper: technical hubs and references

Paths matching this line: technical page, case studies from the same industry and reference hubs.

Need the exact figure for your site?

Open this configuration in Project Studio: change capacity, annual hours, country and financing structure and get the dossier with CAPEX, P&L and the 6-year plan.